On this page, a variant calculation is carried out for the profitability analysis of the following parameters:

  • Interest rate for financing
  • Investment costs
  • Inflation rates (e.g. price change for energy)
  • Price change for operation/maintenance

    Image Removed Image Added


Based on the data collected, possible economic fluctuations can be estimated and their impact calculated. A planned or assumed value is entered in the basic settings. Different scenarios can be entered here, which deviate up and down from the assumed values, in order to estimate the risk of the investment under changed conditions. The expected value comes from the basic settings. The annual (annuity) profit of the project is displayed next to the expected value as an overview in the diagram under "worst case" and "most favorable case".

Image RemovedImage Added